File: 2026.10.26 - Lumenwire Audio - 01 Project Plan.md

Lumenwire Audio: Project Plan

Test case. Made-up company, Sample data. Dates, effort and owners are Gary's proposals unless marked "Marcus".

1. Goal and scope

↑ Back to top

2. Phases and sprints

Sprints are 2 weeks. Phase 2 is set at 2 sprints because two KPIs depend on people outside the interview (telemetry, forecasts) and the data has known gaps. Assumes a break from 21-Dec-26 to 8-Jan-27.

PhaseDatesDeliverablesOwner (role)
1. Discover26-Oct-26 to 6-Nov-26Business Requirements v1.0 approved; open questions Q-1 to Q-11 answered; sign-off on New devices activated (K2) and Forecast accuracy (K5)Business requirements lead; CEO; CFO; VP Sales; Head of Platform Engineering
2. Build KPIs9-Nov-26 to 4-Dec-26 (2 sprints)Measures confirmed on the data, baselines, pace needed, counter-metrics, challenge notesKPI analyst (Kewpie), with the CFO and Head of Platform Engineering
3. Visualise7-Dec-26 to 18-Dec-26 (1 sprint)Story, Standard dashboard, Experimental optionsData visualisation lead (Viktor)
4. Harden11-Jan-27 to 22-Jan-27 (1 sprint)Standards check, validation against the Business Requirements, stakeholder review, fixesStandards lead (Jennifer)
5. Embed25-Jan-27 to 5-Feb-27Handover, owner briefings, monthly review rhythm agreedCEO with the KPI owners

First board-ready dashboard: the first board pack after 5-Feb-27 (about 14 weeks from today).

↑ Back to top

3. MoSCoW

PriorityItems
MustTotal revenue, last 12 months, against the path to A$115m (K1); New devices activated in the field (K2); Software revenue growth (K3); Design wins that ship (K4); Forecast accuracy (K5). K2 and K5 go on page one only after their sign-offs
ShouldOEM stock on hand (K2.1); Share of software revenue from the largest licences (K3.1); Gross margin % (K3.2); Months from design win to first shipment (K4.1); Design wins per quarter (K4.2)
CouldExperimental dashboard views
Won't (this time)Underlying earnings (EBITDA); design wins as a headline; paid features switched on in the field
↑ Back to top

4. Effort estimate (person-days)

PhasePerson-daysAssumptions
1. Discover4Includes three follow-up conversations (CFO, VP Sales, Head of Platform Engineering)
2. Build KPIs14Ledger sign rules, telemetry scaling and de-duplication, CRM stage-date gaps, forecast unit conversion, OEM name matching
3. Visualise6One page, five KPIs, sub-KPI drill views
4. Harden5One round of fixes after stakeholder review
5. Embed3Briefings for four owners
Total32Data access granted by 9-Nov-26
↑ Back to top

5. RAID log

IDTypeDescriptionImpactOwner (role)ActionStatus
R1RiskThe telemetry can't be used as an end-customer view (coverage, test devices, OEM link), so New devices activated (K2) can't go on the pageHHead of Platform EngineeringAnswer Q-4 by 6-Nov-26; if it fails, Gary proposes a replacement for the CEO to approveOpen
R2RiskThe CFO doesn't support Forecast accuracy (K5) as specifiedMCFOAnswer Q-5 by 6-Nov-26Open
R3RiskDesign-win counts are inflated by the bonus (paid per design win, no clawback), so the "record 1,180" overstates the pipelineHVP SalesConversion rate (K4) leads; counts kept underneath; Kewpie checks against invoicesOpen
R4RiskThe dashboard is used to tell the CEO's story rather than test itMBusiness requirements leadEvery KPI traced to the Business Requirements; thresholds agreed before the data is seenOpen
A1AssumptionThe A$115m date is 30 Jun 2028MChair, via the CEOConfirm (Q-1)Open
A2AssumptionSample data reflects the shape of the real dataMKPI analystCheck during Build KPIsOpen
I1IssueNo targets exist for software, design wins, forecasts or FY27 lines that Marcus can vouch forHCFOAnswer Q-2 and Q-3 by 6-Nov-26Open
I2IssueHistory and refresh are unknown for every systemMCFO, VP Sales, Head of Platform EngineeringAnswer Q-6 by 6-Nov-26Open
D1DependencyAccess to the ledger, CRM, telemetry, licences, forecasts and OEM stock reportsHCFO, VP Sales, Head of Platform EngineeringGrant by 9-Nov-26Open
D2DependencyCFO and legal decision on naming OEMs and customersMCFO with legalAnswer Q-7 before Visualise starts (7-Dec-26)Open
↑ Back to top

6. Milestones and approval gates

GateMilestoneApproverTarget date
Stage 1Business Requirements and Project Plan approvedAdam (Head of the Data Team)27-Oct-26
Stage 2KPI calculations, baselines and challenges approvedAdam4-Dec-26
Stage 3Story and dashboard versions approvedAdam18-Dec-26
Stage 4Standards and validation passed; final approvalAdam22-Jan-27
Stage 5Stakeholder sign-off and go-liveMarcus (CEO), then Adam5-Feb-27