File: stage-1-06-stage-1-review.md

Stage 1 Review: what changed

ClearCompare (test case) · 20-Oct-26 · Round 2 of changes, for Adam to review

These are the 7 changes you asked for, shown as Before and After. Use the tabs at the top to see each updated document in full.


Change 1: The open question now asks about target timing

Where: Business Requirements, open questions list (last row)

Open question
Before"What is the cost to the business if nothing changes in the next 6 months?" · Until it's answered: the problem can't be sized in dollars
After"When do we need to reach our KPI targets? Do targets need to be met within the next 6, 9 or 12 months?" · Owner: CCO · Until it's answered: targets use 30-Jun-27 (about 8 months away)

Overlap to note: the list already has a similar question, "What are the target dates for each objective?". Should the older one be removed so the CCO is only asked once? I haven't removed it.


↑ Back to top

Change 2: Timing options added to the net revenue per lead target

Where: Business Requirements, Top 5 KPI "1. Net revenue per lead", Target row, and the same row in Business Requirements with Data Mapping

Net revenue per lead: target
Before"Back to the April to June 2026 level by 30-Jun-27"
After"Back to the April to June 2026 level by 30-Jun-27"
Timing to confirm with the CCO: within 3, 6 or 9 months, or 1 or 2 quarters
· 3 months: by 31-Jan-27
· 6 months: by 30-Apr-27
· 9 months: by 31-Jul-27
· 1 quarter: by 31-Mar-27 (end of the January to March quarter)
· 2 quarters: by 30-Jun-27 (end of the April to June quarter)

How the dates are worked out: months are counted from 1-Nov-26. Quarters are full calendar quarters after the current one (October to December 2026). The current proposal, 30-Jun-27, is the same as the 2-quarter option.

Also fixed: Business Requirements with Data Mapping still said "Back to the Q4 FY26 level". It now says "April to June 2026", the same as the Business Requirements.

Question: the other four Top 5 KPIs also use 30-Jun-27. Should they get the same timing options?


↑ Back to top

Change 3: "KPI Requirements Table" is now "Business Requirements with Data Mapping"

Name
Before"KPI Requirements Table" · file: 2026.10.20 - ClearCompare - 01 KPI Requirements Table.md
After"Business Requirements with Data Mapping" · file: 2026.10.20 - ClearCompare - 01 Business Requirements with Data Mapping.md

Renamed in 7 files (15 places):

It's also renamed on the Miro diagram.


↑ Back to top

Change 4: Gantt chart added to the Project Plan

Where: Project Plan, "Milestones and gates" section (open the "ClearCompare: Project Plan" tab)

Milestones and gates
BeforeA table of 5 milestones and dates only
AfterA Gantt chart above the table: the 5 project phases as bars, with their dates and owners, the 5 approval gates as ◆ markers, and today's date as a dashed line. Hover over a bar or ◆ to see its dates. The table stays underneath

↑ Back to top

Change 5: 2x2 RAID grid added to the Project Plan

Where: Project Plan, "RAID log" section (open the "ClearCompare: Project Plan" tab)

RAID log
BeforeA table only. Short words split across lines ("R- 1", "Op en", "Financ e")
AfterA 2x2 grid above the table: Risks (2), Assumptions (1), Issues (2) and Dependencies (1). Each item shows its impact (High, Medium or Low) as a label, with its owner and action. The table stays underneath, and words no longer split mid-word in any table

↑ Back to top

Change 6: Milestones moved into one lane above the phases

Where: Project Plan, "Milestones and gates" Gantt chart

Gantt chart layout
Before5 phase bars, then 5 separate milestone rows underneath (10 rows)
AfterOne shaded Milestones lane across the top, holding all 5 approval gates as ◆ markers with their names and dates. The 5 phase bars sit underneath (6 rows). Labels are spread over 4 levels so none overlap

↑ Back to top

Change 7: "Business Requirements Document" is now "Business Requirements"

Name
Before"Business Requirements Document", shortened everywhere to "BRD" · file: 2026.10.20 - ClearCompare - 01 BRD.md
After"Business Requirements" everywhere, with no abbreviation · file: 2026.10.20 - ClearCompare - 01 Business Requirements.md

Renamed in 12 files (56 places), including:

Grammar was adjusted where needed, for example "The Business Requirements are the checklist".

Note: the two documents now have similar names, "Business Requirements" and "Business Requirements with Data Mapping". The first is the full requirements; the second is the KPI table with how each KPI is measured.


↑ Back to top

Still waiting on you

↑ Back to top