File: stage-1-05-project-plan.md

ClearCompare: Project Plan

Where we are: Stage 2 of 5 (KPI Development). Stage 1 approved 20-Oct-26

Stage 1
Business Requirements
Gary
Problem, objectives, Top 5 KPIs, Project Plan
Stage 2
KPI Development
Kewpie
Calculations tested on the data
Test case. Linked to Business Requirements v1.0 (20-Oct-26). Dates assume a start on 21-Oct-26 with 2-week sprints.

1. Goal and scope


↑ Back to top

2. Phases and sprints

PhaseDatesDeliverableOwner (role)Gate
1. Discover20-Oct-26Business Requirements v1.0, Project PlanGaryStage 1 approval
2. Build KPIs21-Oct to 03-Nov-26 (Sprint 1)KPI Calculation Pack, baselines, challenge notesKewpieStage 2 approval
3. Visualise04-Nov to 17-Nov-26 (Sprint 2)Standard dashboard, review Artifact, Experimental optionsViktorStage 3 approval
4. Harden18-Nov to 01-Dec-26 (Sprint 3)Finished first draft, standards and validation reportJenniferStage 4 approval
5. Embed02-Dec to 12-Dec-26Owner walk-through, review rhythm agreedCCOStakeholder sign-off

↑ Back to top

3. MoSCoW

PriorityItems
MustThe Top 5 KPIs (net revenue per lead, lead-to-sale conversion, cost per acquisition, speed to contact, 90-day clawback rate), the revenue bridge, revenue shown net of clawbacks, complaint rate shown next to conversion
ShouldThe sub-KPIs (lead mix, health conversion, complaints per 1,000 sales); product area and channel filters
CouldExperimental dashboard options; an estimate of the latest quarter's clawbacks (if finance agrees)
Won't (this time)Agent-level views, partner revenue, website visits

↑ Back to top

4. Effort estimate

PhasePerson-daysAssumptions
Discover1Done
Build KPIs4Data access is ready. Clawback and unmatched-sale rules confirmed
Visualise4Chart templates are reused
Harden3No major standards rework
Embed1One walk-through session
Total13Plus stakeholder time: about 3 hours across the gates

↑ Back to top

5. RAID log

Risks (2)

  • High impactAction owners aren't confirmed, so KPIs may have no one acting on them. Owner: CCO. Action: confirm at the Stage 1 gate
  • High impactThe latest quarter's clawbacks are incomplete, so net revenue looks better than it is. Owner: Finance. Action: decide whether to estimate them

Assumptions (1)

  • Medium impactSample data has the same shape as production data. Owner: Data team. Action: validate on real data before go-live

Issues (2)

  • Medium impact6% of sales can't be matched to a lead. Owner: Data team. Action: exclude from per-lead KPIs and count them
  • Low impactManila call outcomes are blank before Mar-25. Owner: Data team. Action: start contact-speed trends from Mar-25

Dependencies (1)

  • Medium impactSnowflake access for the production build. Owner: IT. Action: request after the prototype

All items are open. The full log is below.

IDTypeDescriptionImpactOwnerActionStatus
R-1RiskAction owners aren't confirmed, so KPIs may have no one acting on themHCCOConfirm at the Stage 1 gateOpen
R-2RiskThe latest quarter's clawbacks are incomplete, so net revenue looks better than it isHFinanceDecide whether to estimate themOpen
A-1AssumptionSample data has the same shape as production dataMData teamValidate on real data before go-liveOpen
I-1Issue6% of sales can't be matched to a leadMData teamExclude from per-lead KPIs and count themOpen
I-2IssueManila call outcomes are blank before Mar-25LData teamStart contact-speed trends from Mar-25Open
D-1DependencySnowflake access for the production buildMITRequest after the prototypeOpen

↑ Back to top

6. Milestones and gates

MilestoneTarget date
Stage 1: Business Requirements approved20-Oct-26
Stage 2: calculations approved03-Nov-26
Stage 3: dashboard version chosen17-Nov-26
Stage 4: first draft approved01-Dec-26
Stakeholder reviewWeek of 02-Dec-26

↑ Back to top

7. Review rhythm after go-live

↑ Back to top